Eminent domain in Texas lets certain pipeline and power line companies condemn an easement across your land if you can’t agree on a price, but only after they follow Chapter 21 of the Texas Property Code. That means you get the Landowner’s Bill of Rights, a written initial offer, a final offer backed by a certified appraisal at least 30 days later, at least 14 days to decide, and then a hearing before three local landowners if you still don’t agree.
You usually can’t stop a line by saying no. But you have more say than most people think, on the price, the easement terms and sometimes the route.
This is general information, not legal advice. If a land agent is at your gate, talk to a landowner attorney who handles condemnation cases.
Who has eminent domain power in Texas
The Texas Constitution says no one’s property can be taken, damaged or destroyed for public use without adequate compensation (Article I, Section 17). “Public use” doesn’t include a taking mainly for economic development or tax revenue. Only government and entities the Legislature has given the power can condemn.
Pipelines
Under the Natural Resources Code, common carrier pipelines have the power of eminent domain (Section 111.019). Gas utilities have it too.
Here’s what surprises people. The Railroad Commission doesn’t decide whether a pipeline is a common carrier. Its FAQ says a T-4 permit is “a permit to operate a pipeline” and “not a determination of whether a pipeline is or is not a common carrier.” The RRC doesn’t approve the need for a pipeline or pick its route, except for some sour gas lines.
The courts decide. In Texas Rice Land Partners v. Denbury Green Pipeline-Texas (2012), the Texas Supreme Court held that a common-carrier permit and a tariff weren’t enough. A CO2 pipeline has to show a reasonable probability, meaning more likely than not, that it will serve the public and not just its owner. Once a landowner challenges it, the burden is on the pipeline company.
Interstate natural gas pipelines are different. Under the Natural Gas Act, a pipeline with a FERC certificate can condemn in federal or state court.
Power lines
Gas and electric corporations can condemn land and easements under the Utilities Code (Section 181.004). An electric utility building a new transmission line generally needs a certificate of convenience and necessity (CCN) from the Public Utility Commission of Texas first.
What the company has to do before it can condemn
Chapter 21 lays out the steps. If the company skips them, that matters.
- Landowner’s Bill of Rights. The company has to give it to you before or at the same time it first tells you it has eminent domain power, and at least 7 days before its final offer (Section 21.0112).
- A written initial offer. It has to include the Bill of Rights, a bold statement saying whether the offer includes damages to your remaining property, the easement or deed itself, and the name and phone number of a company representative (Section 21.0113).
- Appraisal reports. When it makes an offer, the company has to send you, by certified mail, any appraisal reports on your property from the last 10 years (Section 21.0111).
- No gag clause. The offer can’t include a confidentiality provision. You can talk about it with your neighbors, your banker or anyone else.
- A written final offer, at least 30 days later. Before the final offer, the company has to get a written appraisal from a certified appraiser. The final offer has to be at least that amount.
- At least 14 days to respond. Only after that can it file suit.
If a court finds the company didn’t make a bona fide offer, it has to pause the case, order a proper offer, and make the company pay the costs and your reasonable attorney’s fees tied to that violation (Section 21.047).
One catch: if you get your own appraisal and plan to use it, you have to share it with the company too.
What has to be in a pipeline or power line easement
Since 2022, a for-profit company with eminent domain power has to offer an easement that covers certain terms (Section 21.0114). It applies to pipeline easements and to power lines of 60 kilovolts or more.
Pipeline easements
The easement has to address the maximum number of pipelines, the maximum pipe diameter, what can be carried, the minimum burial depth, the maximum width and the location on your land. It also has to cover aboveground equipment, gates and fences, restoring the land, your right to damages from construction and later repairs, and whether the company will double-ditch.
Power line easements
The easement has to describe how the surface will be used, the location and maximum width, how the company will get to it, gates and fences, restoring the land, and your right to damages.
Terms you can ask for
The company has to tell you that you can negotiate damages for certain vegetation and for lost income from disrupted farming or existing leases, based on verifiable loss. You can also ask for liability insurance that protects you.
Read the easement line by line. In my view, the terms matter as much as the check, because they stay with the land.
Power lines: your say on the route happens at the PUC
For a new transmission line, the fight over where it goes happens at the PUC, before anyone condemns anything.
- Notice. The utility has to mail notice to landowners who are directly affected. That means the line would cross your land, or there’s a habitable structure on your land within 300 feet of the centerline (500 feet for lines over 230 kV).
- Deadline to intervene. The notice states it. Under the PUC’s rule it’s 45 days after the application was filed, or 30 days for a new transmission facility.
- Comment or intervene. The PUC’s landowner brochure says comments don’t count as evidence. Intervening makes you a party. You can file evidence, testify and cross-examine witnesses. You don’t need an attorney, but you have to keep up with the case.
- Routing factors. The PUC’s rule says routes must be chosen, where reasonable, to moderate the impact on landowners. That includes looking at existing rights-of-way and property lines.
The PUC doesn’t set what you get paid. The company negotiates easement prices after the route is picked. The review can take up to six months.
One detail ranchers should know. For new transmission rights-of-way, the PUC requires the easement to bar new aboveground structures in the right-of-way. That ban doesn’t cover farm or livestock facilities, storage barns, hunting structures or small sheds.
Step by step: what happens before eminent domain in Texas
Here’s the process, in order, under Chapter 21 of the Texas Property Code. The early steps happen before anyone files a condemnation case. If you can’t agree, the later steps are the case itself.
- They have to have the authority. Only government and entities the Legislature has given the power can condemn, and only for a public use (Texas Constitution, Article I, Section 17). Ask what statute they’re relying on. For a pipeline, a T-4 permit from the Railroad Commission is not a decision that the line is a common carrier.
- They may ask to survey or come onto the property first. Chapter 21 itself doesn’t give them that right. It only says nothing in the chapter stops an entity from seeking survey access under other law (Section 21.0101). For a common carrier pipeline, the Natural Resources Code requires written notice and an indemnification at least two days before a preliminary survey, and it limits where they can go and what they can do (Section 111.019).
- You get the Landowner’s Bill of Rights. They have to give you the Texas Attorney General’s statement before or at the same time they first tell you they have eminent domain power, and at least seven days before the final offer (Section 21.0112).
- A written initial offer. It has to include the Bill of Rights, a bold statement saying whether the offer includes damages to your remaining property, the easement or deed itself, and the name and phone number of a company representative (Section 21.0113). When they make an offer, they also have to send you, by certified mail, any appraisal reports on your property from the last 10 years (Section 21.0111). The offer can’t include a confidentiality provision. You can talk about it.
- The easement terms have to be in the papers. Since 2022, a for-profit company with eminent domain power has to offer an easement that covers certain terms, including the width and location, gates and fences, and restoring your land (Section 21.0114). It applies to pipeline easements and to power lines of 60 kilovolts or more. Those required terms are spelled out earlier in this article.
- A written final offer, at least 30 days later. Before the final offer, the company has to get a written appraisal from a certified appraiser of the property being acquired and any damage to the land you keep. The final offer has to be at least that amount, and it has to include the appraisal if they haven’t already sent it (Section 21.0113). Read that number against what happens to the rest of the ranch, not just the strip. I wrote about the values landowners are offered for easements versus what they should get paid.
- You get at least 14 days to respond to the final offer. Only after that, if you still don’t agree, can the company file a condemnation petition (Section 21.0113).
- If you don’t agree, they can file a condemnation petition. They have to send you a copy by certified and regular mail (Section 21.012). That’s when the formal case starts.
- A hearing before three special commissioners. Within 30 days, the judge appoints three disinterested landowners who live in the county. Each side can strike one, by the later of 10 days after the appointment order or 20 days after the petition was filed. The hearing can’t be sooner than 20 days after they’re appointed, and you get at least 20 days’ notice (Sections 21.014, 21.015 and 21.016). They only decide the money.
- You can object and go to trial. If you don’t like the award, file objections by the first Monday after the 20th day after the commissioners file their findings. Then the case is tried like any other civil case (Section 21.018). You can appeal the trial court’s judgment if you still don’t agree.
The last three steps are the condemnation case. Here’s how that part works.
If you can’t agree: the condemnation case
If you turn down the final offer, the company can file a condemnation petition and must send you a copy by certified and regular mail.
Within 30 days, the judge appoints three special commissioners. They must be disinterested landowners who live in the county. Each side can strike one. The hearing can’t be sooner than 20 days after they’re appointed, and you get at least 20 days’ notice.
The commissioners only decide the money. Per the Attorney General’s Bill of Rights, they don’t decide whether the taking is necessary or public, or change the easement terms.
If you don’t like the award, file objections by the first Monday after the 20th day after the commissioners file their findings. Then the case is tried like any other civil case. Don’t miss that deadline.
Two things to know about the money:
- Costs. If the award is more than the company offered before the case started, the company pays the costs. If it’s the same or less, you pay them (Section 21.047).
- Possession. The company can take possession after the award while the appeal goes on, if it pays or deposits the award and posts bonds (Section 21.021).
What you’re owed
If the whole tract is taken, the measure is local market value at the time of the hearing. If only part is taken, like an easement, the commissioners look at the injury and benefit to you, including the effect on the value of the land you keep (Section 21.042). That’s the remainder. On an easement across a ranch, it can be a big part of the number.
I wrote more about the values landowners are offered for easements versus what they should get paid. For regional averages, see ranch land per acre in Texas, but an appraiser will use local sales.
If the land is taken and the project is canceled, no real progress is made within 10 years, or the land becomes unnecessary within 10 years, you or your heirs may be able to buy it back (Section 21.101).
The Senate bill and federal eminent domain for power lines
Congress is working on a permitting bill that would widen federal eminent domain for power lines. On Nov. 18, 2026, the Senate adopted the Capito substitute to H.R. 2347, 69-27, and voted 65-31 to limit debate. When I checked the morning of Nov. 19, there hadn’t been a final Senate vote, and the House would still have to act.
The substitute would let FERC permit interstate lines of 230 kV or more if a state hasn’t approved them within a year after the application was filed. Permit holders could then use federal eminent domain.
It doesn’t apply inside ERCOT, which carries about 90% of Texas’s electric load. If your land is outside ERCOT, or in another state, keep an eye on it.
What I’d do if a land agent calls
- Ask what authority they’re claiming. Is it a common carrier, a gas utility or an electric utility with a CCN? For pipelines, the RRC can tell you how the line is reported.
- Keep every letter and envelope. Dates matter in Chapter 21.
- Read the easement, not just the offer.
- Get your own appraisal. Make it cover your remaining land, not just the strip.
- Watch for PUC notices. The intervention deadline comes fast.
- Call a landowner attorney early.
Before you buy a ranch, check the title for existing pipeline and power line easements. It’s on my land buying checklist.
Frequently asked questions
Can I refuse a pipeline easement in Texas?
You can refuse to sign. If the company has eminent domain power and follows Chapter 21, it can file to condemn. You can still fight over price, terms and whether it really has the power.
How do I know if a pipeline company has eminent domain?
Ask which statute it’s relying on. The RRC can tell you whether a line is reported as a common carrier or gas utility. A T-4 permit alone doesn’t settle it. The courts decide.
How long do I have to respond to a final offer?
At least 14 days. The final offer has to come at least 30 days after the initial offer.
Who decides how much I get paid?
First, three special commissioners from your county. If you object in time, a judge or jury.
Do I have to pay for my own lawyer and appraiser?
Generally, yes. Chapter 21 makes the company cover your fees in certain cases, like when it didn’t make a bona fide offer or dropped the case.
Can I stop a power line from crossing my land?
You can’t veto it. But you can intervene at the PUC and argue about the route before it’s approved.
Bottom line
Eminent domain in Texas has rules, and most of them are there to protect you. Read the offer and the easement. Watch the deadlines. Get your own appraisal and a good landowner attorney. Questions about a tract? Email jb@jamesbigleyranches.com or call 830-609-8056.
General information, not legal advice. Talk to a Texas landowner attorney about your situation.
Sources
- Texas Constitution, Article I, Section 17: https://statutes.capitol.texas.gov/Docs/CN/htm/CN.1.htm
- Texas Property Code, Chapter 21 (Sections 21.0101, 21.0111, 21.0112, 21.0113, 21.0114, 21.012, 21.014-21.021, 21.042, 21.047, 21.101): https://statutes.capitol.texas.gov/Docs/PR/htm/PR.21.htm
- Texas Government Code, Section 402.031: https://statutes.capitol.texas.gov/Docs/GV/htm/GV.402.htm
- Texas Attorney General, Landowner’s Bill of Rights (rev. Nov. 2025): https://www.texasattorneygeneral.gov/sites/default/files/files/divisions/general-oag/landowners-bill-of-rights-25.pdf
- Texas Natural Resources Code, Chapter 111 (Section 111.019): https://statutes.capitol.texas.gov/Docs/NR/htm/NR.111.htm
- Texas Utilities Code, Chapter 37 and Section 181.004: https://statutes.capitol.texas.gov/Docs/UT/htm/UT.37.htm and https://statutes.capitol.texas.gov/Docs/UT/htm/UT.181.htm
- PUC, 16 TAC 25.101 (Certification Criteria): https://ftp.puc.texas.gov/public/puct-info/agency/rulesnlaws/subrules/electric/25.101/25.101.pdf
- PUC, 16 TAC 22.52 (Notice in Licensing Proceedings): https://ftp.puc.texas.gov/public/puct-info/agency/rulesnlaws/procrules/pr-d/22.52/22.52.pdf
- PUC, “Landowners and Transmission Line Cases at the PUC”: https://ftp.puc.texas.gov/public/puct-info/industry/electric/forms/ccn/Landowners_and_Transmission_Line_Cases_at_the_PUC.pdf
- Railroad Commission of Texas, Pipeline Eminent Domain and Condemnation FAQ: https://www.rrc.texas.gov/about-us/faqs/pipeline-safety-faq/pipeline-eminent-domain-and-condemnation/
- Denbury Green Pipeline-Texas, LLC v. Texas Rice Land Partners, Ltd., No. 15-0225 (Tex. Jan. 6, 2017), applying Texas Rice Land Partners v. Denbury Green, 363 S.W.3d 192 (Tex. 2012): https://www.txcourts.gov/media/1436866/150225.pdf
- Natural Gas Act, 15 U.S.C. 717f(h): https://www.law.cornell.edu/uscode/text/15/717f
- U.S. Senate roll call votes 267 and 268 (Nov. 18, 2026): https://www.senate.gov/legislative/LIS/roll_call_votes/vote1192/vote_119_2_00267.htm and https://www.senate.gov/legislative/LIS/roll_call_votes/vote1192/vote_119_2_00268.htm
- S.Amdt. 6883 text, Congressional Record, Nov. 10, 2026: https://www.govinfo.gov/content/pkg/CREC-2026-11-10/html/CREC-2026-11-10-pt1-PgS5471-2.htm
- ERCOT, About ERCOT: https://www.ercot.com/about